| No |
STEPS OF PROCEDURE |
TIMING |
| 1 |
To decide the workshop/land for building factory and sign MOU |
15 – 30 days |
| 2 |
To prepare the necessary documents for setting up a company/office/branch |
No longer than 10 days |
| 3 |
To complete and submit documents to the local Authorities |
3 days |
| 4 |
To receive the investment license, business registration certificate, stamps and tax declaration |
20 days |
| 5 |
To open bank accounts, capital remittance, staff recruitment |
3 – 5 days |
| 6 |
Official signing of workshop/land sublease contract and land handover |
3 – 5 days |
| 7 |
To apply for land use right certificate(independent step, land owner’s job) |
40 days |
| 8 |
To apply for environmental impact assessment(EIA) report |
Over 20 days |
| 9 |
To apply for construction license ( In case of building factory) |
Over 20 days |
| 10 |
Factory construction work |
Around 90 days |
| 11 |
To apply for the certificate of fire prevention and fighting safe assurance |
Around 30 days |
| 12 |
To complete the office/factory interior decoration |
30 – 45 days |
| 13 |
To deliver and install the machinery and production line |
15 – 20 days |
| 14 |
To execute test operation |
20 – 30 days |